How to record the system origin and updates

The System origin and upkeep page records where your food safety system came from and keeps the log of its reviews. Other pages add changes here that wait for a review, such as a new supplier or a changed critical limit.

Before you start

The system has to stay current as hazards, products and the operation change. If you started from a sector guide or a consultant's template, show how it was fitted to your operation and who confirmed the fit.

  • You are an owner, admin or member. Contributors and viewers see the page read only.
  • Your package includes ISO 22000.

Step by step

1. Open the page

Open System origin and upkeep under Food Safety in the menu.

2. Answer where the plan came from

Under "Did you take a ready-made HACCP plan from somewhere else?", press one of:

  • Yes, we started from something external
  • No, written for this operation

If you press No, go to step 4.

3. Show how the plan was fitted

a. Under What it was based on, write what the plan came from.

b. Under How it was adapted to this operation, write what you changed and why.

To start from a draft, press Draft the adaptation statement. The statement is drafted with AI. The button shows the cost before you press it: 2 credits.

In Proposed adaptation statement, tick the statement to accept it. The person who confirms it still types their own name.

c. Under Confirmed as fitting by, write the name of the person who checked it on the floor.

4. Set the next review

Under Next scheduled review, choose a date.

5. Record an update

Press Record an update, or Record in the update log on a waiting change.

a. Under What prompted it, choose the cause.

b. Under Recorded by, write your name.

c. Under What changed, write what changed, or that nothing did.

d. Under What was looked at, tick each part you reviewed. A waiting change clears only when you tick the parts it needs. The line in the dialog says how many it clears.

e. Press Record.

The update is dated today.

Example from a kitchen

What Krateon saves

  • The origin answer, what the plan was based on, the adaptation and who confirmed it.
  • The next scheduled review date.
  • Each update: date, cause, who recorded it, what changed and what was looked at.
  • The changes still waiting for a review.

Removing an update does not bring back the changes it cleared.

Where it shows up later:

  • HACCP Verification, in the row "HACCP review".
  • The HACCP dossier, section 18.
  • Requirements and the Overview.

If something goes wrong

The quoted texts in the first column appear in the app exactly as shown.

What you seeWhat it meansWhat to do
"This page is not enabled."ISO 22000 is not switched on for your organisation.Contact support at hello@krateon.com.
"Included in {what}" with the button Ask for itYour package does not include ISO 22000.Press Ask for it.
"The records could not be loaded."The page did not load.Press Try again.
"Not answered yet. The clause turns on this answer, so the check stays open until one is given."The origin question has no answer.Press one of the two answers.
"Until the adaptation and who confirmed it are recorded, this reads as a template adopted unchanged."The adaptation or the name of who confirmed it is empty.Fill in both fields.
"Required: {fields}"Recorded by or What changed is empty.Fill in the named fields.
"Waiting over 30 days"A change has waited for a review for over 30 days.Record an update that covers it.
"Nothing ticked yet, so no cause is covered."The parts you ticked do not clear any waiting change.Tick the parts the change needs.
"Could not draft the statement"The draft did not finish.Try again later, or write the statement yourself.